Monte Carlo Simulation for Task Duration

Test Case Example

Objective: To simulate the task duration for a project using a combination of Three-Point Estimation and Monte Carlo Simulation with multiple developers.

Input Values:

Expected Result: A bar chart showing the distribution of estimated durations across 10,000 simulations, with a red vertical line indicating the average estimated duration of approximately 1.88 days.

Explanation: The simulation combines Three-Point Estimation and Monte Carlo Simulation to provide a realistic view of task durations:

As a result, the estimated average duration per developer is approximately 1.88 days, accounting for team effort and project uncertainty.

This simulation combines Three-Point Estimation and Monte Carlo Simulation to estimate project durations.

Inputs:

Output: The chart displays the distribution of estimated task durations in days, with a red line marking the average duration, indicating the most likely completion time for the project.